Shipyard achieves milestone in construction of world’s largest LNG dual-fuel boxship

  • Published
  • by Admin
Jiangnan Shipbuilding positioned the CMA CGM vessel’s 2,200 mt engine and other components in record time with five large cranes and an approximate hundred smaller units.
CMA CGM engine

Shanghai-based Jiangnan Shipbuilding, a subsidiary of China Shipbuilding Group on Tuesday (24 March) said it has successfully installed the second main engine of the world’s largest dual-fuel container ship in record time.

The 23,000 teu container ship is being built for CMA CGM and its main engine weighs at a hefty 2,200 tonnes (mt).

Despite encountering the large size of the engine and manpower shortage due to the COVID-19 pandemic, the company completed the task in six days by using five large cranes for the main components and a hundred smaller cranes for the other parts. 

The earlier projected time to complete the installation was scheduled for nine days. As such, the company has set a record in China for the installation of an engine of this class.  


Photo credit: China Shipbuilding Group
Published: 25 March, 2020